First-pass yield and the capacity effect of rework

Lesson 11.4
12 minOpsida Teknoloji · Last reviewed: October 30, 2026

In one sentence

First-pass yield shows the success of completing a product without correction; the rework load shows the extra resource time the same product consumes.

By the end of this lesson

  • Calculate the first-pass yield rate from the products accepted at first entry.
  • Separate the count of unique products from rework visits and find the final good and scrap rates.
  • Calculate the extra resource load from the number of rework units and the processing time.
  • Combine the main production and rework load on a shared resource and make a feasible capacity decision.

Why it matters

A product coming out good in the end does not mean it was made right the first time. If a product needed correction, readjustment or re-inspection, it has consumed extra resources. The first-pass yield rate preserves this distinction. The denominator is the number of unique products entering the process for the first time; the numerator is those among them accepted without rework. Seeing the same product a second time is not counted as a new entry. If the product identity is not preserved, the records can show production higher than it is. As a result, both the quality indicator and the capacity calculation are distorted. For this reason the product history carries more information than the final status alone.

The rework load often stays outside the daily production table. When a worker or machine set aside for the main operation spends time again on the same part, the opportunity to make new products falls. Even if the resource is separate, the load does not disappear; it moves to another work center. In these two cases the same total time can produce different flow results. First it is explained which resource was used for how many minutes, and then the capacity on the calendar is assessed. Counting the number of units leaving a station may not show all the work spent at that station. If especially re-inspection and handling after correction are left out of scope, the extra load looks incomplete.

The final good rate is the ratio of unique products accepted at the end of the period to the first entries. It answers a different question from the first-pass rate. A high final good rate can be useful in meeting customer need, but it must not hide a low first-pass success or a heavy correction load. Scrap, products waiting for rework and products whose outcome is still open are also kept as separate states. Assuming a record that has not yet concluded to be good raises the ratio early. If the same time window and the same product set are not preserved, the comparison loses its meaning. For products that enter within the period and complete afterward, the closing rule must be written in advance.

The aim in this lesson is not simply to label rework as negative. When needed, a nonconforming product can be salvaged by a safe and verified operation. But the feasibility of the correction, the re-acceptance condition and the resource effect must be clear. Removing the final inspection to cut time, or counting a product that has been corrected as a new product, is not a solution. A lasting improvement raises the first-pass success while protecting the acceptance condition. Cost, lead time and resource load are reported as separate results. A proposal that reduces the rework quantity becomes stronger when it is shown with new data that the same source of defect does not recur later.

Formula

First-pass yield (%) = Unique products accepted at first entry ÷ Unique products at first entry × 100

Final good rate (%) = Unique products accepted in the final status ÷ Unique products at first entry × 100

Rework load (min) = Number of rework visits × Visit time (min/visit)

Shared-resource total load (min) = Main operation load + Rework load

Resource load per good product (min/unit) = Total resource load ÷ Number of final good products

Load increase (%) = Extra load ÷ Main operation load × 100

Unlock the rest of this lesson with an Academy account

Create a free Academy account with your work email address; it can be used once it is approved.

  • Step-by-step instructions
  • Worked example with real numbers
  • Where the method misleads
  • Common mistakes
Create a free Academy account