Netting and Time Phasing in Material Requirements Planning

Lesson 20.2
12 minOpsida Teknoloji · Last reviewed: October 30, 2026

In one sentence

MRP nets the gross requirement from the bill of materials against available stock and on-time receipts, and calculates when a new order must be started.

By the end of this lesson

  • Calculate the component requirement of 100 units of product with the bill-of-materials coefficient.
  • Find the net requirement of 100 units using on-hand stock and on-time receipts.
  • Derive the planned receipt and start dates from the lead time.
  • Choose the appropriate decision for a late receipt, a quality block or a start date in the past.

Why it matters

Material requirements planning, MRP for short, determines how much of which part will be needed and when, through interlinked calculations. The demand for the finished product is converted into components with the usage quantities in the bill of materials. This is the gross requirement. When the available material in hand and the receipts confirmed up to the moment of need are deducted, the quantity that still has to be covered is found. The value of the calculation is that it makes purchasing and production needs visible together with their dates. On the other hand, a correct net quantity alone does not prove that the material has actually been secured or that production capacity is sufficient.

Availability matters as much as the stock count. Material set aside for quality reasons, allocated to another order or physically not found cannot be used as free stock. The date of a confirmed purchase order is also compared with the requirement date. Counting a quantity that will arrive after the need as if it closed today's gap is making a wrong delivery promise with a correct subtraction. The record therefore contains not only a quantity; the part identity, unit of measure, available date and status are held together. An uncertain receipt is not shown at the same confidence level as a verified one.

Time phasing is the backward offsetting of the net requirement. The lead time is subtracted from the date the receipt is needed to find the date the order must be started. This time may not consist only of processing on the machine; it may include the defined sum of supply, transport and acceptance conditions. Adding the same wait twice or leaving out the required acceptance time changes the result. The working calendar and the calendar duration must also be kept apart. A date found without knowing which days the duration counts cannot be accepted as an executable start date. The assumption behind the date calculation should be as visible as the quantity calculation.

The MRP calculation is decision support; it is not an assurance that fills in missing data by itself. A wrong bill-of-materials coefficient spreads to all lower levels. A start date that is already in the past cannot be solved by opening an order in the past. First, the feasible options with the material at hand, open orders and real capacity are examined. It must also be known for which components the shop-floor pull system generates orders; the same requirement is not released to production a second time. Netting, time phasing and release thus pass through separate checks. Even if the calculation is correct, a wrong decision at the boundary can create excess stock or a delivery gap. For the numerical scenarios in the lesson quizzes as well: This dataset was generated synthetically for training; it does not represent a real business, employee or customer study.

Formula

Gross requirement (component units) = Product quantity (product units) × Usage (component units/product unit)

Net requirement (units) = max(0, Gross requirement + Target period-end stock − Previous available stock − Confirmed on-time receipt)

Period-end available stock (units) = Previous stock + Confirmed receipt + Planned receipt − Gross requirement

Planned start date = Planned available receipt date − Defined lead time

Lead time made up of processing, inspection, transport and waitingStart: 180 s4424141880Waiting −40 s: 140 s4424141840Shaping 44 sDeburring 24 sCheck 14 sMove 18 sWaiting 80 sValue-creating work: 68 s68 ÷ 180 = 37.8% of the total180 − 40 = 140 s
In a separate flow, 68 s of the 180 s lead time (44+24+14+18+80) is value-creating work (37.8%); cutting the waiting by 40 s makes the total 140 s. In MRP, backward offsetting uses the defined lead-time scope, not only the processing time; this figure is not a net requirement calculation. This dataset was generated synthetically for training; it does not represent a real business, employee or customer study.

Unlock the rest of this lesson with an Academy account

Create a free Academy account with your work email address; it can be used once it is approved.

  • Step-by-step instructions
  • Worked example with real numbers
  • Where the method misleads
  • Common mistakes
Create a free Academy account