Planned Maintenance, Spare Parts and Work Orders

Lesson 18.4
12 minOpsida Teknoloji · Last reviewed: October 30, 2026

In one sentence

Planned maintenance is a working arrangement in which not only the time of the job but also its scope, skill, part and return-to-production verification are prepared in advance.

By the end of this lesson

  • Separate the preparation before the stoppage in a work order from the equipment stoppage.
  • Add up the maintenance and verification times and calculate whether the window is sufficient.
  • Find the quantity usable for the job by subtracting the part set aside from physical stock.
  • Show numerically why the simple ratio found from the averages of 150 min and 15 min does not cover planned maintenance and external waiting.

Why it matters

That a date is written in the maintenance calendar does not show that the job can be done on that date. When the equipment stops, the part cannot be found, the suitable person goes to another job or the restart check may not have been defined. Planned maintenance brings these gaps out before execution. The work order links which equipment will get what work, what resources are required and how completion will be verified. The document is not only a retrospective record of time. It is a shared preparation tool so that the job can start safely and return to production in an acceptable state. A job with an incomplete scope finishing in a very short time does not mean the plan was successful.

Spare parts preparation is a critical part of this arrangement. Not all of the quantity visible in the warehouse may be open to every job. A part set aside for another job, one whose suitability has not been verified or one with a different technical specification is not counted as usable stock. That a part is cheap does not reduce its criticality; a single missing part can hold up the entire maintenance. At the same time, keeping every part without limit is not a solution. Need, replenishment time, failure consequence and alternatives are assessed together. This lesson does not replace a detailed stock policy; it teaches separating the physical quantity from the truly usable quantity so that a work order can start. Suitability, time and reservation status must appear in the same record.

The maintenance window is the real time interval in which production may be affected. Preparations that can be made without stopping the equipment can be arranged outside this interval; but the labor load of the preparation does not disappear. Establishing the safe working condition, the maintenance job and the return-to-production verification may be required within the window. Removing one of them is not planning the job better. Counting all the times as parallel without examining the job sequence and resource conflicts is also wrong. The sufficiency of the plan is tested not only by the total minutes but by whether the required skills and resources can be present at the same time. The condition for stopping and replanning in case of an unexpected finding must also be explained in advance.

The scope of the availability indicator becomes important again here. The simple ratio of 90.91% found with an MTBF of 150 min/failure and an active MTTR of 15 min/repair does not include the maintenance window and external waiting. Therefore it cannot be presented as the effectiveness of the whole shift or period. Removing planned maintenance from the record may make the ratio look nicer; but it does not increase the time available to the customer. Conversely, that planned maintenance has no benefit at all cannot be deduced just from this denominator growing. The purpose of the maintenance and its expected technical effect are tested separately. The outcome seen with the same time boundary shows how the plan can be improved.

When part use takes place, the stock record and the work order must verify each other. If a part set aside for preparation but not used still appears reserved when the job closes, it may needlessly block the next plan. If the record of a used part is not deducted, this time the next job relies on a quantity that does not actually exist. For this reason closing is not only a time report. Actual consumption, the suitable material returned and any need for a new part are also explained. The difference between the record and the physical state must be resolved before the next maintenance window. In this way planning does not carry a past error into the future list of ready jobs.

Formula

Usable parts (pcs) = Suitable physical stock − Stock set aside for another job

Maintenance stoppage (min) = Safe execution preparation + Maintenance job + Return-to-production verification + Waiting within the stoppage that does not overlap with these

Window remainder (min) = Allocated window − Maintenance stoppage

Simple availability (%) = 150 min ÷ (150 min + 15 min) × 100 = 90.91%

Period run share (%) = Run time ÷ Whole stated period time × 100

From planned time to the ideal-time equivalent of good productionOEE = 80% × 80% × 95% = 60.8%450 minPlanned−90 minAvailability80%−72 minPerformance80%−14.4 minQuality95%273.6 minGood output
The figure is a separate scope example: when 90 min of stoppage, 72 min of performance loss and 14.4 min of quality loss are subtracted from 450 min of planned time, 273.6 min of ideal-time equivalent of good production remains. This equivalent is not actual run time. Which maintenance enters the planned production time must be defined in advance; the 80% availability in the figure has a different denominator from the 90.91% simple ratio in the lesson. This dataset was generated synthetically for training; it does not represent a real business, employee or customer study.

Unlock the rest of this lesson with an Academy account

Create a free Academy account with your work email address; it can be used once it is approved.

  • Step-by-step instructions
  • Worked example with real numbers
  • Where the method misleads
  • Common mistakes
Create a free Academy account