Lean Manufacturing Calculators

A free suite of lean and industrial-engineering calculators — takt, OEE, cycle time, flow and more. Instant results, no sign-up. The same formulas built into Yamazo Studio's Lean Operating Desk.

Available now

Takt Time Calculator
Takt = Net available time / Customer demand
OEE Calculator
OEE = Availability × Performance × Quality
Cycle Time Calculator
Saving = (Current − Target) × Volume × Work days × Rate
Little's Law Calculator
WIP = Throughput × Lead time (L = λ × W)
Process Cycle Efficiency (PCE) Calculator
PCE = Value-add time / Total lead time × 100
Pitch Calculator
Pitch = Takt × Pack size
Kanban Calculator
N = ⌈ (D × LT × (1 + α)) / C ⌉
SMED Savings Calculator
Saving = (Current − Target) × Changeovers/day × Work days
Line Balance Efficiency Calculator
Efficiency = Total work content / (Stations × Cycle time)
Rolled Throughput Yield (RTY) Calculator
RTY = FPY1 × FPY2 × … × FPYn
DPMO Calculator
DPMO = (Defects / (Units × Opportunities)) × 1,000,000
Sigma Level Calculator
σ = NORMSINV(1 − DPMO/1,000,000) + 1.5
Process Capability Calculator (Cp / Cpk)
Cp = (USL − LSL) / 6σ · Cpk = min(Cpu, Cpl)
EOQ Calculator
EOQ = √( (2 × D × S) / H )
Safety Stock & Reorder Point Calculator
SS = Z × σ_d × √LT · ROP = demand × LT + SS
Standard Work Calculator
Operators = ⌈ total manual time / takt ⌉
Heijunka Calculator
Units/variant = demand / variants · pitch = takt
Throughput Calculator
Throughput = units produced / time period
Pareto Analysis Calculator
Sort desc → share % → cumulative % → vital few ≤ 80%
5S Audit Calculator
Score = Σ pillars / 25 → %
Kaizen ROI Calculator
ROI = (savings + one-time − cost) / cost × 100
MTBF & MTTR Calculator
MTBF = uptime / failures · MTTR = downtime / failures